Many homeowners and architects wait until the drawings are finished to bring in a builder. By then, the biggest decisions about structure, budget and materials are already made, and changing them costs time and money. Here’s why we recommend starting the conversation much earlier.
We’re usually engaged during schematic design, and it’s a great time to join the team. The design is taking shape, but the consultants haven’t committed to their solutions yet. Any adjustments can be made while they’re still easy.
Structure and budget. We’re often asked how structural requirements will affect the budget. Clients often say “take the complexity out,” but the complexity usually lives in the structure. Being part of the team early lets us spot the conflicts where mechanical systems and architectural details meet the structure, before they’re drawn into the plans.
Materials and lead times. Materials are one of the easiest places to manage both budget and schedule. Steel, wood, tile, windows and stone can all carry long lead times, and many are sourced from Europe. Knowing that early keeps orders on schedule and gives the owner real choices.
We provide estimates at three stages:
Each pricing exercise can take several weeks. Pricing at each stage keeps the budget and the design moving together, so there are no surprises when the drawings are done.
At Caju, the window orders had to respect datums from a custom steel staircase, a steel deck, concrete control joints and a concrete chimney. None of them had been built yet. Steel went in aligned to finish details that wouldn’t be installed for a couple of years. That level of coordination only works when the builder is at the table while the design is still being shaped.
When you first meet with a builder, ask:
If you’re early in the design of a Jackson Hole home, start a conversation with Wind River Builders. The sooner we’re involved, the more we can help.